Barn.5

The concrete work has finally been completed.  Last of the flatwork was done on Tuesday and the water line was trenched in too.  The lid for the cellar was finished on Monday.  The last of the excavation should be finished today.  The septic tank should be placed by Monday.  I’ll just need to plumb the tank and leeching field, then I can begin to get the grading finished.  It will be nice to get something growing around here.  The ground is so dry that it is either hard as concrete or if disturbed by machinery it has turned to dust.  

I would normally be a little concerned that there is rain forecast for this morning, but that should all dry up before it reaches us.  I would gladly clean out a little runoff if we were to get a measurable rainfall.

Advertisements

4 Comments

  1. Ed said,

    July 26, 2012 at 11:39 AM

    Is the septic tank for the barn or are you just replacing the house one while you have all the equipment there?

  2. Woody said,

    July 26, 2012 at 5:37 PM

    Ed..It is separate system for the barn only.

  3. Ron said,

    July 27, 2012 at 4:59 AM

    It is interesting to see how he formed the root cellar lid. It makes my formwork back in the day seem like overkill to the 10th degree. But I guess I'm still alive to joke about it, which is the main thing. šŸ™‚

  4. Woody said,

    July 27, 2012 at 4:52 PM

    Ron…There is a wall on 16's down the center and 3/4 ply with a three inch overhang on the top of the walls. IT's a lot more solid than it appears, but I totally agree that safe is better than sorry.


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: